The Obligated-Disbursed Gap: Permitting, Not Concrete, Is America's Infrastructure Bottleneck

The key IIJA statistic is not how much money was allocated, but how little has been converted into finished projects.

GAO’s July 2026 review found that of $574.7 billion in IIJA budget authority across DOT, EPA, Interior, and NTIA, roughly 76% had been obligated, but only 54% of obligated funds had been disbursed. The 22-point gap is the clearest measure of America’s infrastructure bottleneck.

The constraint is not capital. It is institutional throughput.

Formula Funding Solved Capital Allocation

IIJA largely distributes money through formulas tied to factors such as population and lane miles. Highway funding and State Revolving Fund grants are designed to move capital automatically rather than through competitive selection.

The result:

What formula funding does not solve is project execution.

Why Obligated Funds Stall

Three constraints dominate.

1. Administrative and Political Friction

Beginning in 2025, agencies reviewed awards against new policy priorities.

GAO reported:

Formula funding reduces competitive risk. It does not eliminate political risk.

2. Delivery Workforce Constraints

State DOTs and municipal agencies must design, permit, approve, and contract projects.

Many face:

The result is growing dependence on engineering consultants.

3. Environmental Review Timelines

Historically:

Review Type Typical Duration
Average federal EIS ~4.5 years
Transportation EIS ~6.5-7+ years
2021-2024 median after reforms ~2.2-2.4 years

Even after streamlining, environmental review remains a multi-year gate for large projects.

The bottleneck sits between appropriation and construction: design, review, and permitting.

Where the Economic Rent Accrues

The market is increasingly rewarding firms that help capital move through the approval pipeline.

Layer Evidence Signal
Engineering & environmental consulting AECOM backlog $26.2B; design book-to-burn above 1.0x for 22 straight quarters; Tetra Tech revenue and margin expansion Pricing power and capacity scarcity
Compliance & permitting services AEC M&A multiples rose to 13.2x EV/EBITDA in 2025 from 11.1x in 2024 Capital targeting throughput capacity
Public-sector delivery Budgets rising faster than staffing Institutional strain
Physical construction Strong demand but exposed to labor, materials, retainage, and bonding risk Lower-quality economics

Two signals stand out:

  1. AECOM’s persistent book-to-burn above 1.0x indicates demand arriving faster than projects can be worked through.
  2. Tetra Tech’s margin growth exceeding revenue growth suggests pricing power rather than simple volume growth.

Private capital is reinforcing the message.

Metric 2024 2025
Average AEC multiple 11.1x 13.2x
PE deal volume Baseline +32.7%
Median deal value Baseline +84.9% to $110M

The clearest example was WSP’s acquisition of TRC at roughly 15.9x EV/EBITDA.

Sponsors are paying for design, permitting, compliance, and project-delivery capacity, not concrete-pouring capacity.

The Deregulation Risk

This rent is not guaranteed.

The administration has actively targeted NEPA-related bottlenecks:

This creates two opposing forces.

Force Mechanism Effect
Successful deregulation Faster reviews Compresses compliance-related rents
Regulatory transition Agencies rewriting procedures amid litigation and policy changes Creates additional near-term compliance demand

Even if compliance burdens fall, design and workforce constraints remain. Labor shortages cannot be removed by rewriting regulations.

The Political Clock

The thesis also depends on continued funding.

Recent legislation has already rescinded portions of unobligated infrastructure-related balances, demonstrating that funds remaining in the pipeline are vulnerable.

The larger issue is timing:

This matters because throughput rents are time-sensitive.

Capital that gets obligated, permitted, and disbursed before funding changes becomes durable.

Capital stuck in the queue may not.

The Core Thesis

The data supports a simple conclusion:

America’s binding infrastructure constraint is institutional throughput, not construction capacity.

Evidence includes:

However, this is a perishable rent.

The durable edge is not “permitting bureaucracy lasts forever.”

The edge is the ability to move capital through design, permitting, and approval pipelines before political or regulatory conditions change.

Indicators to Watch

Indicator What It Measures
Obligation vs. disbursement gaps Delivery-capacity strain
AECOM, Jacobs, Tetra Tech, WSP, Stantec backlog and book-to-burn data Demand relative to engineering supply
AEC vs. construction M&A multiples Where scarcity value exists
State DOT and municipal staffing versus budget growth Institutional capacity
Agency-specific NEPA rule changes and litigation outcomes Durability of compliance rents
IIJA reauthorization terms Future size of the funding pipeline

The market has largely priced the existence of infrastructure spending. It is increasingly pricing the entities that can convert appropriated dollars into approved, executable projects.